Report 11/2014: Near-miss at Llandovery level crossing

Near-miss at Llandovery level crossing, Carmarthenshire, 6 June 2013.

R112014-140515-Llandovery.pdf

At around 05:56 hrs on 6 June 2013, train 2M43, the 04:34 hrs passenger service from Swansea to Shrewsbury, was driven over Llandovery level crossing in the town of Llandovery in Carmarthenshire, Wales, while the crossing was open to road traffic. As the train approached the level crossing, a van drove over immediately in front of it. A witness working in a garage next to the level crossing saw what had happened and reported the incident to the police.

The level crossing is operated by the train’s conductor using a control panel located on the station platform. The level crossing was still open to road traffic because the conductor of train 2M43 had not operated the level crossing controls. The conductor did not operate the level crossing because he may have had a lapse in concentration, and may have become distracted by other events at Llandovery station.

The train driver did not notice that the level crossing had not been operated because he may have been distracted by events before and during the train’s stop at Llandovery, and the positioning of equipment provided at Llandovery station relating to the operation of trains over the level crossing was sub-optimal.

RAIB identified that an opportunity to integrate the operation of Llandovery level crossing into the signalling arrangements (which would have prevented this incident)was missed when signalling works were planned and commissioned at Llandovery between 2007 and 2010. The RAIB also identified that there was no formalised method of work for train operations at Llandovery.

RAIB has made six recommendations. Four are to the train operator, Arriva Trains Wales, and focus on improving the position of platform equipment, identifying locations where traincrew carry out operational tasks and issuing methods of work for those locations, improvements to its operational risk management arrangements and improving the guidance given to its duty control managers on handling serious operational irregularities such as the one that occurred at Llandovery.

Two recommendations are made to Network Rail. These relate to improvements to its processes for signalling projects, to require the wider consideration of reasonable opportunities to make improvements when defining the scope of these projects, and consideration of the practicability of providing a clear indication to train crew when Llandovery level crossing, and other crossings of a similar design, are still open to road traffic.

Response to recommendations:

  • RAIB will periodically update the status of recommendations as reported to us by the relevant safety authority or public body
  • RAIB may add comment, particularly if we have concerns regarding these responses.

RAIB Recommendation response for Llandovery

Published 10 December 2014